PoliticsRishikesh-Karnaprayag rail project set for December 2029 completion: RVNL CMD
The Rishikesh-Karnaprayag railway line, developed by RVNL, aims for completion by December 2029 with 78% overall progress and 97% tunnel excavation completed. The 125-km route passes through multiple Uttarakhand districts, featuring 16 main tunnels and 12 escape tunnels, and includes 11 of 19 major
By Project Chintan Newsroom · 28 Aug