Edayippalam Road Reopening Delayed as Malappuram Braces for Heavy Rainfall
District authorities postponed the restoration of traffic on the Vengara-Malappuram road following a site inspection by an inter-departmental expert committee. While debris clearance is complete, a standing orange alert and soil instability risks have kept the transit route closed.
Key takeaways
- Traffic restoration on the Vengara-Malappuram road is deferred until Friday due to an orange rain alert and soil instability concerns.
- A massive cleanup operation removed 373 truckloads of debris from the Edayippalam landslip site near Panakkad.
- The district administration is launching a crackdown on illegal quarries and unauthorized constructions following the Monday landslide.

Safety Concerns Halt Traffic Restoration
Plans to reopen the Vengara-Malappuram road on Thursday were suspended as an orange alert for heavy rain persists across the district. Following a significant landslip at Edayippalam on Monday, a multi-disciplinary expert committee conducted a field assessment to determine the safety of the hillside. The team included representatives from the Geology, Soil Conservation, Motor Vehicles, Police, and Public Works departments, alongside disaster management analysts.
Although technical teams confirmed the road is physically motorable, they issued a warning regarding slope integrity. Experts noted that continued heavy precipitation could cause waterlogged soil to lose structural strength, risking further collapses. The initial incident on Monday saw mud, boulders, and trees slide into both the road and the Kadalundipuzha river, nearly striking several individuals and journalists.
Scale of the Clearance Operation
Recovery efforts at the site, located approximately 200 metres from the home of Industries Minister P.K. Kunhalikutty, required a massive logistics operation. Work began on Tuesday with four earthmovers and 47 lorries transporting 238 truckloads of debris. By Wednesday, an additional 135 truckloads were cleared using three earthmovers and 23 lorries. In total, 373 truckloads of soil and rock were removed from the thoroughfare.
District Collector Vinay Goyal recognized the efforts of Fire and Rescue Services, led by Malappuram station officer M. Abdul Gafoor, and various volunteer groups. Personnel utilized fire engines and mobile tank units to clear blocked drains and remove remaining slush from the pavement. As a safety measure, 20 households in the immediate vicinity remain evacuated while officials monitor the area for further soil movement.
Regulatory Crackdown on Illegal Mining
The landslip has prompted the district administration to launch a wider investigation into illegal land use. Authorities announced that joint teams from the Revenue, Police, and Geology departments will now target unauthorized laterite and granite quarries. The initiative includes identifying unpermitted constructions and removing encroachments along national and state highways. To enforce these measures, the district will establish 24-hour check-posts to inspect tipper lorries and other vehicles transporting quarry materials.
Key Facts
- A total of 373 truckloads of earth were removed from the Edayippalam landslip site over two days.
- The site of the collapse is situated 200 metres from the residence of Industries Minister P.K. Kunhalikutty.
- Approximately 20 houses were evacuated to prevent casualties during the unstable weather period.
- An expert committee warned that waterlogged soil poses a recurring threat to slope stability.
- The district will implement round-the-clock vehicle inspections to curb illegal quarrying operations.
Source: The Hindu — National
Related stories
Kerala Braces for Extreme Downpours as IMD Issues Red Alerts for Three Districts
Scientific Alert: Kerala Faces Rising Threats from Mesoscale Cloudbursts
Deadly Terrain: Why Kerala’s Geography and High Population Density Fuel Landslide Risks

