Kadapa District Sees ₹182.74 Crore in New Road Construction

Officials reported the completion of 586 km of roads valued at ₹182.74 crore in the undivided Kadapa district. Ministers urged acceleration of land acquisition for national highways.

· 1 min read
Updated

Key takeaways

  • Approximately 586 kilometers of roads, valued at ₹182.74 crore, have been completed in the undivided Kadapa district.
  • Government officials reviewed the progress of road construction projects in Pulivendula on August 14, 2026.
  • Ministers have instructed officials to speed up land acquisition for national highway projects in the district.

State government officials have announced the completion of 586 kilometers of roads, valued at ₹182.74 crore, within the undivided Kadapa district.

The announcement was made on Friday, August 14, 2026, during a meeting in Pulivendula. Ministers B.C. Janardhan Reddy (Roads and Buildings) and S. Savitha (district in-charge) presided over the review of road project progress.

Key Facts

  • Roads totaling 586 km and worth ₹182.74 crore have been constructed in the undivided Kadapa district.
  • Ministers B.C. Janardhan Reddy and S. Savitha reviewed road project progress in Pulivendula on Friday, August 14, 2026.
  • Officials informed that 93 road works were initiated in Kadapa district; 29 are complete, 58 are in progress, and six are in the tender stage.
  • In Pulivendula constituency, nine projects valued at ₹10.55 crore were undertaken, with five completed and the rest in progress.

What Happens Next

Ministers directed officials to expedite the land acquisition process for national highways planned within the district. They also instructed officials to match the pace of road construction, emphasizing the Chief Minister's priority for road development across the state despite funding challenges.