Andhra Pradesh to link 100 temple towns with ₹120-cr road push
Public roads are being built to over 100 temple towns in Andhra Pradesh, funded at ₹120 crore to cover about 205 km. As of the Deputy Chief Minister's update, roughly 40% of the works are finished with 26 roads completed and ready for inauguration.
Key takeaways
- A ₹120 crore project will connect more than 100 temple towns in Andhra Pradesh via about 205 km of roads.
- Approximately 40% of the works are completed, with 26 roads finished and ready for inauguration.
- Completed routes include roads to Antarvedi and Ahobilam Narasimha temples, among others, with additional works ongoing in several districts.

What Happened
Andhra Pradesh’s Panchayat Raj and Rural Development department has undertaken a project to construct connecting roads to more than 100 major temple towns. The initiative has a total budget of ₹120 crore and aims to span about 205 km. Deputy Chief Minister and PR&RD Minister K. Pawan Kalyan stated that approximately 40% of the works are completed.
Among the roads developed, 26 have been completed and are prepared for inauguration. Completed routes include access roads to Narasimha temples at Antarvedi and Ahobilam, the Sri Gattu Venkataramana Swamy temple at Madanapalle, the Devaraya Nallagangamma temple, Singirikona Lakshmi Narasimha Swamy temple, Thalupulamma Lova, and the I.S. Jagannadhapuram ghat. Additional projects are underway on the Konaseema Tirumala Vadapalli embankment road, the Arthagiri Sri Anjaneyaswamy temple road, and the Malleswara Swamy temple road in Puthalapattu constituency. In Sri Sathya Sai district, road works cover 72 km and are ongoing.
Why It Matters
The program is framed as infrastructure improvement aimed at easing movement for devotees to temple towns, addressing reported gaps in road connectivity. The Deputy Chief Minister has directed officials to address the identified issues after field visits and public representations about the roads’ poor conditions. The scale—covering 205 km across more than 100 temple towns with a substantial budget—suggests a visible push to integrate religious sites with regional road networks.
Background
The department described the project as a response to gaps in the road network that hinder devotees’ travel to temple towns. Public feedback during field visits prompted officials to prioritize these connectivity improvements.
Key Facts
- Budget: ₹120 crore
- Distance targeted: 205 km
- Number of temple towns targeted: more than 100
- Completion status: about 40% of works completed
- Completed roads ready for inauguration: 26
- Examples of completed routes include access roads to Antarvedi, Ahobilam, Madanapalle, and other temples
- Ongoing works include Konaseema Tirumala Vadapalli embankment road and several temple roads in Puthalapattu
- Sri Sathya Sai district works: 72 km in progress
What Happens Next
The statement notes ongoing progress with additional road works underway in multiple locations, including embankment and temple access routes. No specific new completion dates are provided beyond the current progress and ongoing works.
Sources reviewed
Project Chintan independently synthesized and analyzed information cross-checked across the sources listed above.
Related stories
TN to study alternate sites for Chennai’s second airport, Hosur project in view
Jagan cites drop in AP government school enrolment amid private-school rise

Kerala sets Oct 12–17 for Plus One improvement exams