Nandi Hills Ropeway Project Advances Amidst Pending Environmental Clearances
Construction has commenced on the lower terminal of the Nandi Hills cable car system despite a lack of federal forest department approval. The project cost has surged to over 240 crore rupees as developers await permission to build the upper terminal and transit towers.
Key takeaways
- Lower Terminal Point construction in Madaku Hosahalli is 20% complete, including foundations for a food court and parking facilities.
- Project costs escalated from 93.40 crore to 240.17 crore rupees due to upgraded safety standards and land acquisition needs.
- The Ministry of Environment, Forest and Climate Change has yet to approve five acres for the Upper Terminal Point and 12 support towers.
- Component deliveries from Italian firm Leitner are currently suspended until environmental and archaeological clearances are secured.
- Dyanamicx Ropeway Private Limited will operate the 2.94-km system for 30 years, paying an escalating annual fee to the government.

Lower Terminal Progress and Technical Specifications
Development of the long-awaited Nandi Hills ropeway has transitioned into the physical construction phase, with 20% of the Lower Terminal Point (LTP) now complete. Situated in Madaku Hosahalli village near the Kanive Basaveshwara Swamy temple, the base station site spans seven acres. The developer, Dyanamicx Ropeway Private Limited (DRPL), has finished terminal building work up to the second floor and completed the foundation for a planned food court. The site will eventually accommodate 200 cars, 150 motorcycles, and bus parking to manage the influx of tourists near Bengaluru.
The engineering specifications for the 2.94-kilometer ropeway underwent rigorous scrutiny before breaking ground. The Indian Institute of Technology (IIT) Dharwad conducted a three-month peer review of the structural designs and soil stability. While initial projections pegged the cost at 93.40 crore rupees, the budget has ballooned to 240.17 crore rupees. Officials attribute this increase to the adoption of CEN safety standards, high-quality pillar materials, and the inclusion of modern amenities.
Regulatory Hurdles at the Summit
While work proceeds at the foothills, the project faces a significant bottleneck regarding the Upper Terminal Point (UTP). The Ministry of Environment, Forest and Climate Change (MoEFCC) has not yet granted clearance for the five acres of land required at the hilltop. This regulatory delay has created a domino effect, stalling essential No Objection Certificates from the Archaeological Survey of India (ASI), the Fire Department, the Pollution Control Board, and local gram panchayats.
Technical procurement has also hit a standstill. Although the Department of Tourism contracted the Italian firm Leitner to supply ropeway components, the first delivery remains on hold pending forest clearance. The missing permits cover not only the summit station but also the installation of 12 support towers along the transit corridor.
Operational Terms and Government Oversight
The agreement between the state and the private developer outlines a 30-year operational window. Under these terms, the government will receive an annual fee starting at 1.60 crore rupees, featuring a 5% yearly escalation. To address the current administrative stalemate, Tourism Minister K. J. George has established a coordination unit in New Delhi aimed at fast-tracking the necessary environmental approvals through the Parivesh portal.
- Project Length: 2.94 km
- Current Investment: 240.17 crore rupees
- Terminal Location: Madaku Hosahalli village
- Safety Standard: CEN (European Committee for Standardization)
Source: The Hindu — National
Related stories

Supreme Court Fast-Tracks Plea Demanding Organizer Liability for NEET-UG Protest Violence

DMK Legislator Markandayan Secures Bail Following Threats Against Chief Minister Vijay

